IZMIR – ISTANBUL BRIDGE AND ROAD-WAY PROJECT

North Anchoring Construction: A total of 44,000 m³ of concrete; 20,680 m² formwork; 6,500 tons of iron work will be carried out at foundation and abutments.
Progress: 48.24% at North Anchorage Block; 36.14% at Triangular Pier.
Sidespan Pier works are awaiting the site delivery by employer.

 

Project Date
November, 2013 -continuing

Project Location
Minsk, Belarus

Client
Belmart Plaza

Employer
Belmart Plaza

Consultant

BELMART PLAZA SHOPPING CENTER- MULTILEVEL CARPARK PROJECT

The turn-key project with a gross building area of 39,450 m²; complete design and construction works are being carried out.
Overall progress of Civil, Electrical and Mechanical Works is 45%.

 

Project Date
March 2012 - Continue

Project Place
MINSK
BELARUS

Client
FLAGSHIP
RESORTS
LLP

Management
FLAGSHIP
RESORTS
LLP

Consultant

HILTON MINSK HOTEL (5 STARS)

“5 Star and 200 room. Totally 22.000 m2 construction area. Hilton International Hotel design and construction works. Turn-key project.”

 

ON GOING PROJECTS

• IZMIR–ISTANBUL BRIDGE AND ROAD-WAY PROJECT

• HILTON MINSK HOTEL (5 STARS)
• BELMART PLAZA AVM ÇOK KATLI OTOPARK PROJESİ
Çamlık Mah. İkbal Cad. Dinç Sok. No: 31 Kat:1 34770 Ümraniye - İstanbul
T: +90 (216) 642 92 82 F: +90 (216) 642 92 81
akort@akortcons.com www.akortconstruction.com


Home Page | About Us | Fields of Activity | On going Projects | Completed Projects | Quality Policy | Client Portfolio | Contac US